The U.S. is seeing a growing trend in the use of public-private partnerships (P3s) for the delivery of transportation infrastructure through an infusion of infrastructure funds into the revenue- strapped public infrastructure market. The Federal Highway Administration defines a P3 as “a long-term partnership arrangement between a government agency and a private sector party…resulting in the private sector party providing public infrastructure and/or services that are traditionally delivered by the public sector.” P3s, in their most basic form, are a mechanism for a government sponsor/partner to shift project-related risks to the private partner/investor.
While discussions of the P3 delivery model tend to focus on the “bottom line” potential, few understand one of the basic motivators behind a successful P3 project: the appropriate sharing of risk.
Understanding Shared Risks
The use of various P3 delivery models brings to bear the ways in which risks can be shared between public and private entities. A key objective of a P3 is strategic distribution of risk to maximize the benefit to the public—otherwise known as the Value for Money (VFM). Distribution or allocation of specific risks between public and private partners is primarily determined by the rule of control: the risk should be allocated to the party best able to control the risk; if neither party is able to control a risk, then the risk should be shared.
The traditional infrastructure delivery model is usually referred to as a Design-Bid-Build (DBB) process. In the DBB process, the public agency assumes all risks with the exception of actual construction risks. Construction risks are assumed by the private constructor in lieu of a payment for delivering the project. By contrast, in a full Concession delivery approach, the private entity assumes the largest percent of project delivery, financing, revenue, operation, and maintenance risk.
General protocols for determining and assigning risks include:
Variations in the risk regime are driven by the following considerations:
Achieving a Win-Win
The success of any P3 agreement is contingent upon having an alignment of interests and a solid contract for delivery of the project between the public and private entities, regardless of the model to be used. Among the keys to this success are:
The successful P3 does not happen without overcoming challenges, which may typically include:
Today’s infrastructure market is complicated and growing in complexity as qualified private entities vie for roles typically assumed by public agencies. The transfer of risk from the public agency to the private entity is a critical consideration in a public agency’s strategy to become involved in public-private partnerships. Understanding these relationships can result in better projects and the long-term alignment of interests for the benefit of the public.
The graphic below depicts the shift in risk areas among various delivery models. Areas of risk are summarized for each major portion of project delivery, from project initiation through construction and operation. Those areas highlighted in a darker color represent those risks assumed by the public agency. Those areas highlighted in the lighter color represent those risks assumed by the private entity. Those areas shaded in both colors depict risks shared by both the public and private entities.
Moving from left to right, the delivery models show a greater assumption of risk by the private entity and additional shared risks between the two entities.![]()